Although architects aren't shy about citing "means and methods" it seems many of them don't understand the full impact of what they're referring to. Turning again to the AIA A201, here's what Article 3 says (my italics).
§ 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
§ 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters.